# Fears emerge 20-week roadworks on major Sheffield road could over-run, amid concerns for businesses

- URL: https://talkfuse.com/story/fears-emerge-20-week-roadworks-on-major-sheffield-road-could-over-run-amid-concerns-for-businesses/
- Published: 2026-08-21T16:17:23+00:00
- Original publisher: The Star (Sheffield)
- Original article: https://www.thestar.co.uk/news/traffic-and-travel/fears-emerge-20-week-roadworks-on-major-sheffield-road-could-over-run-amid-concerns-for-businesses-8934323
- Topics: Sheffield

## Key points

- Gas pipe replacement roadworks in Sheffield's Crookes are progressing slower than planned; after four weeks the project has only advanced from Springvale Road to the Punchbowl pub
- Businesses report revenue losses of up to 40 per cent, compounded by parking restrictions being implemented ahead of where construction actually is located
- Local politicians are requesting improved communication from contractor Cadent, including a dedicated contact point and better coordination of traffic management measures

## Summary

A major infrastructure project to replace aging gas pipes in Sheffield's Crookes area has fallen behind schedule just weeks after beginning work in late July. The 20-week replacement programme has only progressed from Springvale Road to the Punchbowl pub after nearly four weeks, suggesting possible delays despite engineers citing engineering challenges as a complicating factor. The slower-than-expected pace has coincided with parking restrictions being scheduled to take effect near The Ball pub, a location the work has not yet reached.

Local businesses are reporting significant financial strain as a result of the disruption, with some claiming takings have dropped by as much as 40 per cent. The situation has been worsened by poor coordination between the work schedule and the implementation of traffic management measures, leaving traders confused and unable to access clear information from contractor Cadent about delivery logistics. Councillors Ruth Milson and Minesh Parekh, along with Sheffield Hallam MP Olivia Blake, have called on Cadent to provide clearer timescales, designate a single point of contact for businesses, and align parking restrictions with the actual pace of construction work.

---
Summarised by TalkFuse (https://talkfuse.com/). Quote the original publisher for the reporting and link this page for the summary and discussion.