## Key points

- Grid bottlenecks leave much Scottish wind power unused.
- Gas plants replace the curtailed wind generation.
- Balancing costs could reach £8 billion by 2030.

## Summary

Scotland’s wind power is often curtailed because transmission cables cannot carry all the electricity south to areas of demand. Gas-fired power stations in England then make up the shortfall, leaving consumers to fund both the unused wind generation and replacement power.

Experts estimate that only 60 per cent of Scotland’s renewable electricity can currently reach consumers. The cost of balancing the grid by switching wind off and gas on was £1.9 billion last year, and could rise to £8 billion by 2030 without upgrades; the National Audit Office says £70 billion of investment is needed by 2031. Scotland has more than 4,700 operational wind turbines, while work to upgrade the Harker substation near Carlisle is under way.

---