Teravolt looks to cannibalize older industries to meet AI power demand
Teravolt, a London-based AI infrastructure firm, argues that meeting soaring AI power demand means repurposing older industrial assets, such as Bitcoin mining farms, aluminium smelters and disused thermal power plants, into datacentres rather than waiting for new grid capacity to be built. This matters because forecasters expect a substantial shortfall between electricity supply and AI compute demand within the next decade, and building new grid infrastructure takes far longer than constructing a datacentre, meaning existing energy assets with ready-made power connections, permits and staff offer the fastest route to closing the gap.
Gartner predicts global datacentre power demand will hit 132 GW in 2026 and 290 GW by 2030, while Teravolt itself forecasts a 240 GW shortfall by 2036. The firm says AI compute generates far higher revenue per megawatt than legacy industries, for example an aluminium smelter and is therefore economically incentivised to convert brownfield industrial sites, particularly in Eastern and Southern Europe where such sites remain comparatively cheap, into AI infrastructure, with executives predicting this "cannibalisation" of older industries will eventually spread to other regions.
In short
- Teravolt wants to convert old industrial sites into AI datacentres
- Predicted power shortfall makes repurposing faster than building new grid capacity
- AI compute earns far more per megawatt than industries like aluminium smelting
Steelman: both sides, in good faith
The strongest fair case each way — we don't pick a winner.
The case for
Repurposing underused industrial sites could bring AI datacentre capacity online faster than waiting years for new grid infrastructure, using existing power connections, permits and skilled staff. If AI compute produces substantially more value per megawatt than legacy uses, conversion may attract investment to neglected regions and help meet demand while new electricity supply is developed.
The case against
Diverting sites and power from smelters, mining operations and other industries could weaken local employment and production, and higher-value AI use does not by itself show that conversion serves the wider public interest. Relying on existing connections may also shift electricity scarcity onto communities and remaining businesses, while treating a company’s long-range demand forecast as a reason to convert assets risks locking in decisions before the scale and benefits of future AI demand are clear.
Explained simply
AI models are trained and run in datacentres, which use large amounts of electricity. Expanding the power grid can take years, so some companies are looking at industrial sites that already have power connections and permits.
Teravolt is a London-based firm that develops infrastructure for AI computing. It argues that sites such as Bitcoin mining farms, aluminium smelters and closed power stations could be converted into datacentres, especially in parts of Eastern and Southern Europe where industrial land may cost less.
The proposal reflects forecasts that datacentre electricity needs will rise sharply, though estimates of future demand and any supply gap vary. Converting industrial sites could bring new investment and make more power available to AI, while reducing the role of some existing industries.