Trump admin hit with $461M lawsuit as embassy fight started under Biden comes back to haunt State Dept
B.L. Harbert International has sued the Trump administration for more than $461 million, saying the State Department withdrew from a settlement over costs the company incurred on overseas diplomatic construction during the COVID-19 pandemic. The case matters because Harbert says it followed government directions to keep work and procurement moving, while the government later failed to honour the agreed payment.
The lawsuit, filed in the US Court of Federal Claims, concerns 12 projects across four continents, including sites in Turkey, Iraq, Thailand, Morocco, Mexico and Central America. Harbert says it was working on 17 embassy and consulate projects when the pandemic began, and that labour costs at the Guatemala City embassy alone reached about $1.3 million a month; it alleges officials agreed to a $370 million settlement in September 2025, but the government paid only $501,636 before reversing course.
In short
- Harbert is seeking more than $461 million from the Trump administration.
- The dispute concerns pandemic costs on 12 diplomatic construction projects.
- Harbert says a $370 million settlement was largely unpaid.
Steelman: both sides, in good faith
The strongest fair case each way — we don't pick a winner.
The case for
Harbert’s strongest case is that it kept costly overseas projects moving during an extraordinary disruption, relying on government directions and then on an agreed settlement to cover pandemic-related expenses. If officials approved the $370 million settlement and the company incurred costs in response, withdrawing from it after paying only a small fraction could undermine fair dealing and contractors’ confidence in government commitments.
The case against
The government’s strongest case would be that a large settlement must be supported by the contract, the documented costs and proper approval, and that officials should not pay public money if the agreement was unauthorised or the amount was not adequately justified. It could also argue that pandemic-era decisions were made under changing conditions, so the court should determine what costs the government was actually responsible for rather than treating the alleged settlement as automatically binding.
Explained simply
B.L. Harbert International is a US construction company that builds diplomatic facilities for the State Department, the agency responsible for US foreign relations and its embassies and consulates. These projects can involve long schedules, specialist workers and materials sourced from different countries.
The case concerns extra costs the company says it faced when COVID-19 disrupted construction and supply chains. Harbert says it kept work and purchasing moving in line with government directions, while the government later agreed to cover some costs. The dispute matters because it raises questions about how public contracts handle unexpected expenses and whether agreed payments should be honoured.