Supreme Court urged to protect homeowners’ property rights in data center power fight
A group of Maryland property owners has asked the US Supreme Court to review a dispute over a developer’s access to their land. The case concerns whether PSEG Renewable Transmission may enter private property to survey and study a possible power line, raising questions about landowners’ rights as data centre development increases demand for electricity.
The proposed transmission line would stretch 67 miles, but its construction is still being explored. The landowners argue that a lower federal court did not properly follow Maryland law when it allowed the surveys; the dispute also reflects wider tensions in Maryland and neighbouring Virginia over expanding data centres and the energy infrastructure needed to support them.
In short
- Maryland owners seek Supreme Court review of land access for power line surveys.
- The proposed transmission line would run 67 miles.
- The case comes amid growing data centre energy demand.
Steelman: both sides, in good faith
The strongest fair case each way — we don't pick a winner.
The case for
Allowing limited surveys could help planners determine whether a transmission route is feasible before committing to a major project, supporting reliable electricity supplies as data centre demand grows. If access is subject to clear legal safeguards and compensation for any harm, proponents may argue that carefully constrained surveying serves a wider public interest while preserving owners’ ability to challenge construction.
The case against
Private property rights include a meaningful say over who enters land, and a proposed project’s public benefit does not automatically justify access before it is approved. The landowners’ argument is that courts must apply Maryland law correctly and protect owners from being made to bear the intrusion and risks of exploratory work for a private developer’s possible project.
Explained simply
Data centres are large facilities that store and process digital information. They use substantial amounts of electricity, so building more of them can increase demand for new power lines and other energy infrastructure.
PSEG Renewable Transmission is a company exploring a possible 67-mile power line in Maryland. To assess the route, it has sought access to private land for surveys and studies; the line is still under consideration, and this dispute concerns access for that early work rather than permission to build it.
The property owners say a lower federal court did not apply Maryland law correctly when it allowed the surveys, and they have asked the US Supreme Court to review the case. The outcome could clarify how landowners’ rights apply when companies seek access to property to study proposed energy projects.