Reform and Tory councils lose High Court bid to halt construction of UK’s largest solar farm
Two councils have failed in a High Court bid to challenge government approval of the Springwell Solar Farm in Lincolnshire, clearing the way for the project to proceed. The ruling matters because the 800-megawatt development is set to become the UK’s largest power-generating solar farm.
Reform UK-run Lincolnshire County Council and Conservative-led North Kesteven District Council argued that the government had not properly assessed effects on rural villages, landscapes and high-quality farmland. Mr Justice Kimblin ruled that claims of a procedural defect were not arguable. The 1,280-hectare site, which includes battery storage, is expected to generate enough electricity for 180,000 homes.
In short
- High Court rejects two councils’ challenge to Springwell.
- The 800-megawatt project covers 1,280 hectares.
- It is expected to power 180,000 homes.