Hyperscale data centers use 2% of US electricity
A study estimates that 403 large US data centres used between 68 and 99 terawatt-hours of electricity from May 2024 to April 2025. That represents 1.5 to 2.2 per cent of US electricity use, making the findings a useful baseline as the rapid expansion of computing infrastructure raises questions about power supply and emissions.
The researchers estimated the centres produced 21 to 31 million metric tonnes of carbon dioxide, around 0.5 per cent of US fossil fuel emissions. Their electricity mix was 54 per cent fossil fuels, 25 per cent renewables and 21 per cent nuclear. The study could not separate AI workloads from other data services, excluded 272 unverified facilities, and did not count on-site generation such as natural gas turbines.
In short
- Hyperscale data centres used up to 2.2% of US electricity.
- Their estimated emissions reached 31 million tonnes of CO₂.
- The study could not isolate AI workloads or on-site generation.
Steelman: both sides, in good faith
The strongest fair case each way — we don't pick a winner.
The case for
The estimates provide a useful measure of data centres’ growing demand for electricity and associated emissions, information that can help planners and the public weigh expansion against energy and climate goals. Even though the study has limits, establishing a baseline can support better decisions about where new facilities are built and how they are powered.
The case against
The figures cover a substantial but incomplete sample and cannot distinguish AI use from other services, so they may not show how much electricity particular technologies consume or how quickly demand is changing. Because on-site generation was excluded and many facilities were unverified, the estimates should be treated cautiously before using them to justify broad policy or investment decisions.