Stymied datacentre projects threaten global AI revolution
- Around half of 250 major global datacentre projects face delay or cancellation.
- Strained power grids are the biggest barrier to AI infrastructure.
- Local opposition, costs and chip shortages also stall projects.
Large-scale datacentre projects around the world are being delayed or cancelled just as demand for the computing power behind artificial intelligence surges. The Uptime Institute, which rates datacentres, found that of 250 global projects above 100MW announced between 2021 and 2024, roughly half will either not go ahead…